News Flash

Home

Posted on: February 10, 2022

Main Street Sewer Upgrades

1 - Main St Construction

The existing sewer collection system in Main Street was developed in stages from the 1940s to the late 1990s. It is being replaced and improved prior to the Caltrans’ "Yreka Rehab Project". 

The current work is replacing all sewer laterals, manholes, and extending them to new main lines. This will greatly simplify the collection system and maintenance issues. 

Approximately 4,250 feet of the main line will be rehabilitated with a cured-in-place pipe lining. Roughly 2,000' will replaced by pipe bursting to increase hydraulic capacity. Approximately 1,000' will be replaced via open-cut trench method to realign the main in the center turn lane.

Facebook Twitter Email

Other News in Home

2023 Master Fee Schedule Update

Posted on: January 6, 2023
Burn Permits Required

Yard Waste Burning

Posted on: November 2, 2022
dog license

Dog License Renewals Due

Posted on: March 25, 2022
300ppi_Square_Logo

General Plan 2044

Posted on: February 23, 2022
Calendar - Presidents Day

City Hall closed 2/21/22

Posted on: February 18, 2022
green waste days

Green Waste Days

Posted on: March 30, 2022
CC-Dumpday-SiskiyouCounty

Free Dump Day - March 19, 2022

Posted on: March 16, 2022